Application for Water, Sewer, and/or Natural Gas Tap – Capacity Commitment
Customer Service
173 NW Hillsboro St.
Lake City, Florida 32055-3918
Telephone (386) 752-2031
Application for Water, Sewer, and/or Natural Gas Tap – Capacity Commitment
TAP AND IMPACT APPLICATION PROCESS
Step 1
The customer submits a completed tap application.
Step 2
The Utility Service Coordinator sends a copy of the application to:
Distributions & Collections Director
Water Treatment Plant Director
Waste Water Treatment Plant Director
Natural Gas Director
Building Official
Step 3
Utility Staff will review the application and determine:
Available Water capacity, if applicable
Available Sewer capacity, if applicable
Available Gas capacity, if applicable
The approval process may take up to 2 weeks to complete.
Step 4
If no issues exist, then a cost estimate will be prepared. The Utility Service Coordinator will notify the customer.
Step 5
Once all fees are received, the Utility Service Coordinator will generate a Tap work order. The Utility Department will schedule for the tap to be completed.
It may take up to 3 weeks to complete the work order. The customer will be contacted if additional time is needed for completion.
Step 6
The utility account is established and will begin billing all utility fees applicable on the date that the water or gas meter is set. (example: water, sewer, and natural gas)